Roof is Completed PDF Print E-mail
Tuesday, 10 March 2009 02:35
The roof of the building was completed on 3rd March 2009 only 3 days beyond the scheduled date of February 28th, may be due to the fewer number of days in February than in other months. We must congradulate the Building Committee for their dedication. It was completed at a cost of Rs. 483,319.

The Building Committee expects to complete plastering of walls of the first floor and levelling of the floor before end of March, provided we  manage to collect adequate funds for it.

The photographs show the completed roof, which is beautiful. It is cool under it like under the shade of a tree